FIRE SUPPRESSION / SPRINKLER SYSTEMS

Navigating the permitting process for sprinkler systems in Washington, DC can feel like an overwhelming maze. Between coordinating with DC Water for flow tests and approvals, submitting detailed plans to the Department of Buildings (DOB), and managing multiple inspections, even the smallest oversight can cause costly delays. Whether it’s understanding water line requirements, sizing meters, or obtaining permits for installation, the process demands precision and experience. At BBCDC Construction, we simplify the complexity. Our team handles every step—ensuring compliance, keeping timelines on track, and delivering seamless sprinkler solutions so you can focus on what matters most.

At BBCDC Construction, we specialize in optimizing the utility and sprinkler installation processes for your construction projects in Washington, DC. Our dedicated team ensures that each phase is executed with precision and efficiency, adhering to timelines that minimize delays.

WATER LINE (Approx. 90–140 Days)

Countermaps and GIS Map via DC Water: 10–20 days

Meter Sizing Worksheet RFI via DC Water: 10–20 days

Engineering Plans and Permits via Engineer: 30–45 days

DDOT Plans and Permits via Horizontal Excavator: 30–45 days

Excavate, Install Utilities, Backfill, and Restore Site: 7–10 days

SPRINKLER (Approx. 50–75 Days)

Letter in Lieu of Flow Test via DC Water: 10–20 days

Sprinkler Plans and Permits via Sprinkler Installer: 30–45 days

Sprinkler Installation: 7–10 days