FIRE SUPPRESSION / SPRINKLER SYSTEMS
Navigating the permitting process for sprinkler systems in Washington, DC can feel like an overwhelming maze. Between coordinating with DC Water for flow tests and approvals, submitting detailed plans to the Department of Buildings (DOB), and managing multiple inspections, even the smallest oversight can cause costly delays. Whether it’s understanding water line requirements, sizing meters, or obtaining permits for installation, the process demands precision and experience. At BBCDC Construction, we simplify the complexity. Our team handles every step—ensuring compliance, keeping timelines on track, and delivering seamless sprinkler solutions so you can focus on what matters most.
At BBCDC Construction, we specialize in optimizing the utility and sprinkler installation processes for your construction projects in Washington, DC. Our dedicated team ensures that each phase is executed with precision and efficiency, adhering to timelines that minimize delays.
WATER LINE (Approx. 90–140 Days)
• Countermaps and GIS Map via DC Water: 10–20 days
• Meter Sizing Worksheet RFI via DC Water: 10–20 days
• Engineering Plans and Permits via Engineer: 30–45 days
• DDOT Plans and Permits via Horizontal Excavator: 30–45 days
• Excavate, Install Utilities, Backfill, and Restore Site: 7–10 days
SPRINKLER (Approx. 50–75 Days)
• Letter in Lieu of Flow Test via DC Water: 10–20 days
• Sprinkler Plans and Permits via Sprinkler Installer: 30–45 days
• Sprinkler Installation: 7–10 days
EPA LEAD-BASED PAINT RENOVATION, REPAIR, AND PAINTING ACTIVITIES #NAT-F254732-1
DISADVANTAGED BUSINESS ENTERPRISE (DBE)
DC CERTIFIED BUSINESS ENTERPRISE (CBE)
CERTIFICATION NUMBER: LSD34313092025
SMALL BUSINESS ENTERPRISE (SBE)
LOCAL BUSINESS ENTERPRISE (LBE)
DC LICENSE # 410521000429
CAGE CODE 8MRD4
MD MHIC 6178021